Project #118 - CNG Project

- Location
-
4004 S. Park Ave.
- Status
-
In Design
- Total Estimated Project Cost
-
$13,402,550.00
- Expenditures to Date Through 4/30/2015
- $829,025.00
- Estimated date of completion as of 5/7/2014
-
7/31/2016
- Project Contact
-
Brian Conte (837-6319)
View this project on the Projects Map
- Description
-
The project will be completed in two (2) Phases. Overall scope is to replace CNG plant, and install & modify fuel islands at Thomas O. Price Service Center (TOPSC).
Phase I - Design Development Level. This phase establishes a 50% design development document with construction cost estimate. Completed.
Phase II - Installation and modifications of fuel islands and construction of CNG plant. This phase includes completion of the design effort and bid process.
- Additional Info
-
- Designation(s)
-
City of Tucson, Capital Improvement Project
- Last Update
-
5/14/2015
Project #118 - Status
06-May-15 |
Phase II - The construction Contractor has mobilized and equipment is being ordered.
|
10-Apr-15 |
Phase II - The project has a construction contract award to D. L. Withers Construction. The project has Mayor and Council approval.
|
10-Mar-15 |
Phase II - The project is in the bid award phase. The project has Mayor and Council approval.
|
13-Feb-15 |
Phase II - The project is biding. The project has Mayor and Council approval.
|
07-Jan-15 |
Phase II - The project is biding. The project has Mayor and Council approval. |
09-Dec-14 |
Phase II - The design is complete and submitted to Development Services for Building Code Plan Check. The project has Mayor and Council approval. |
06-Nov-14 |
The design is complete and submitted to Development Services for Building Code Plan Check. The project has Mayor and Council approval. |
02-Oct-14 |
Status is the same as previous month. |
09-Sep-14 |
Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval. |
11-Aug-14 |
Project status is the same as July 2014. |
02-Jul-14 |
Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval. |
10-Jun-14 |
The status is the same as April 2014. |
07-May-14 |
Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval. |
08-Apr-14 |
Project completion. |
07-Mar-14 |
Phase I - the 50% Design Development (DD) level is complete. |
10-Feb-14 |
Phase I - the Schematic Design (SD) level is complete. |
13-Jan-14 |
No change in status. |
06-Dec-13 |
Phase I - the Schematic Design (SD) level is complete. |
07-Nov-13 |
Phase I - the Schematic Design (SD) level is complete.
|
08-Oct-13 |
Phase I - the Schematic Design (SD) level is complete.
|