Project #138 - Silverbell Landfill Water Quality Revolving Fund (WQARF)Pump and Treat System

- Location
- Goret/Silverbell
- Status
- Pre-Design
- Total Estimated Project Cost
- $5,458,000.00
- Expenditures to Date Through 4/30/2015
- $165,354.00
- Estimated date of completion as of 4/15/2015
- 10/31/2016
- Project Contact
- Andrew Quigley
- Description
- Remove Landfill volatile organic compound (VOC) contamination from the groundwater and also protect down-gradient wells and the City's Sweetwater Recharge Facility.
- Additional Info
- Designation(s)
- City of Tucson, Capital Improvement Project
- Last Update
- 5/14/2015
Project #138 - Status
06-May-15 | Currently reviewing and updating Conceptual design. |
15-Apr-15 | Starting RFP Process for Design and Construction. |
18-Mar-15 | No status report provided this month. |
13-Feb-15 | Selected Contractor developing Final Design RFP. Initial internal review scheduled for 2/2015. |
12-Jan-15 | Contractor selected for Final Design RFP. |
09-Dec-14 | RFP issued for the development of RFP for Final Design with consultant selection ongoing. |
04-Nov-14 | October 9, 2014 - Conceptual design and cost estimates complete. Request for Proposal (RFP) for final design under development. |