08-Jun-12 |
Construction of base project is 100% complete. Installation of additional, owner-requested items is still in progress. Exhibit is open to the public. |
08-May-12 |
Construction of base project is 100% complete. Installation of additional, owner-requested items is still in progress. Exhibit is open to the public. |
05-Apr-12 |
Construction of base project is 100% complete. Installation of additional, owner-requested items is still in progress. Exhibit is open to the public. |
06-Mar-12 |
Construction is substantially complete for the entire project. Punch list is in progress. |
07-Feb-12 |
The Barn, Elephant Restraint Device, Life Support System (Pool Treatment/Circulation System), and Exhibit are substantially complete. Punch list is in progress. Visitor area landscape, irrigation and fencing are in progress and expected to be complete in mid February. |
09-Jan-12 |
Shotcrete rockwork, site grading, barn exterior, drywall, painting & pool circulation system are substantially complete. Final electrical, plumbing, mechanical & hydraulic systems for barn are in progress. Sidewalks, landscape, hydroseeding and irrigation are in progress. Solar system to be installed in the near future. |
01-Nov-11 |
Shotcrete rockwork, site grading and barn exterior are substantially complete. Final electrical, plumbing, mechanical and drywall for barn and pool circulation system are in progress. Sidewalks, landscape, hydroseeding and irrigation are in progress. Solar system to be installed in the near future. |
06-Sep-11 |
Construction is in progress and on schedule.
Next Milestone: Substantial Completion of Construction |
07-Jul-11 |
Next Milestone: Substantial Completion of Construction |
07-Jun-11 |
Construction is in progress and on schedule. |
16-Dec-10 |
The Ground breaking ceremony was held at 1:00 pm on the seven-acre expansion which is the biggest ever at the zoo. |